An architect proposes a recovery time objective of 36 hours for a process whose maximum tolerable downtime is also 36 hours, arguing the two should match. Why does NIST SP 800-34 disagree?
Show the answer
Answer: D. Work such as reprocessing data must also fit inside the tolerable downtime, so the objective must normally be shorter.
The recovery time objective must ensure the maximum tolerable downtime is not exceeded, and time spent reprocessing after restoration counts against it, so it is normally shorter.
Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 > 3.2.1 Determine Business Processes and Recovery Criticality