A budget review asks which alternate site type is cheapest to maintain and what it costs the organisation in return. What does NIST SP 800-34 say?
Show the answer
Answer: B. The cold site is the least expensive to maintain, but may need substantial time to acquire and install equipment.
Cold sites cost least to maintain but may take substantial time to acquire and install equipment, with warm sites sitting between the two extremes.
Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 > 3.4.3 Alternate Site