A programme manager schedules the security control assessment for a new claims system as a single event in the week before the authorisation decision, arguing that any earlier assessment would examine an unfinished system. The assessment lead pushes back. Which correction should the lead offer?
Show the answer
Answer: B. Assessment belongs at several points across the development life cycle rather than only at the authorisation decision
Control assessment is expected at multiple life-cycle points so defects surface while remediation is cheap; a single pre-authorisation event guarantees late, costly findings.
Source: NIST SP 800-53A Rev. 5 (NIST) — SP 800-53A Rev. 5 > Abstract