CISSP study material · question 82 of 500
The board asks what the output of the risk framing step should actually be, since framing produces no control decisions of its own. What does an organisation produce by framing risk?
Show the answer
Answer: D. A risk management strategy stating assumptions, constraints, tolerance, and priorities and trade-offs.
Framing establishes the context for later decisions and yields the risk management strategy. Registers, milestone plans and system security plans are outputs of assessment, response or system-level work.
Source: NIST SP 800-39 (NIST) — SP 800-39 > 2.1 Components of Risk Management