A continuity coordinator finds the achievable recovery time objective is twelve hours while the maximum tolerable downtime, fixed by regulation, is six. Management will not fund a faster solution this year. What does NIST SP 800-34 direct?
Show the answer
Answer: A. Raise a plan of action and milestones documenting the gap and the plan to mitigate it.
Where the objective cannot be met immediately and the tolerable downtime is inflexible, SP 800-34 says to initiate a plan of action and milestones documenting the situation and its mitigation.
Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 > 3.2.1 Determine Business Processes and Recovery Criticality