- Home
- All questions
- Question 136
CISSP study material · question 136 of 500
A coordinator beginning a business impact analysis asks which existing artefact gives the starting point for judging outage consequences. Under NIST SP 800-34, what is it?
Show the answer
Answer: A. The system's FIPS 199 availability impact level.
SP 800-34 makes the FIPS 199 category for the availability security objective the basis of the business impact analysis, with further process analysis layered on top.
Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 > 3.2.1 Determine Business Processes and Recovery Criticality