A project team plans to conduct its business impact analysis after the system goes live, when real usage data will be available. What does NIST SP 800-34 recommend instead?
Show the answer
Answer: B. Perform it during initiation, and repeat it during development or acquisition if the design changes.
The business impact analysis belongs in the initiation phase, and may need to be conducted again during development or acquisition as the design and components change.
Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 > 3.2 Conduct the Business Impact Analysis